Between the loading dock and the final plinth lies what is often the tightest passage of the whole project.
Data center equipment logistics and lifting covers the transport, handling and positioning of heavy or oversized equipment: transformers, high-rating switchboards, chillers, standby generators. It is a short phase with little tolerance for improvisation: access, floor loading and clearance constraints are poorly discovered on delivery day.

Equipment is selected on its performance and delivered through a door. The usual chronology of projects means the second question arrives after the first, sometimes too late: the machine is ordered when someone discovers it will not pass the airlock, that the intermediate slab will not take its rolling load, or that the only crane path passes over a room in service.
We therefore study the access route at the same time as the equipment selection: successive clearances, headroom, permissible floor loading, crane capacity, road and timing constraints. It is an inexpensive study whose absence gets paid for in building alterations.
On a live site, a lift is not only a matter of capacity: it is a matter of consequence. A path over a room in service, vibration transmitted through the structure, a blocked fire access route - any one of these can rule out a method that is otherwise technically sound.
We treat these operations as high-risk work: written method, approved paths, negotiated slots, and for every phase the question of what happens if it has to stop midway. That is what allows them to proceed without putting operations at risk.
The data center packages this expertise covers are shown in full, the others are dimmed. Click a package for detail.
Medium-voltage switchgear distributes and protects; transformers step the voltage down to usable low voltage. These are very long-life assets, where reuse saves several quarters of lead time.
The last line of backup, with its fuel tanks and bunding. A generator only counts once its load acceptance has been tested for real, several times - untested redundancy is a hypothesis.
Chillers and free cooling, producing the chilled water. In the French climate a large share of the year can be covered without compression - provided the loop accepts warm enough water.
From the access study through to final positioning on the plinth.
Four stages, the first of which governs all the others.
Survey of the complete route, from delivery point to plinth. Conclusions issued before the equipment is ordered wherever that is still possible.
Written method statement, lift plans, road permits, work slots and operational approvals.
Transport, lifting and handling within the agreed slots, with protection measures in place.
Placement, packing and levelling, then handover to the team responsible for connections.
Before ordering heavy equipment, ideally. It is the only point at which an access constraint can still steer the choice of equipment rather than force an alteration to the building. An access study costs a fraction of widening an airlock or strengthening a slab.
Yes, that is the most common case. These operations are run with a written method statement, approved paths, slots negotiated with operations, and a prepared response for every phase that might have to stop.
Yes, transport and permits included. Power transformers and high-capacity chillers frequently fall into that category, and permit lead times must be built into the programme well in advance.
Three very different people land on these pages. Take the door that fits you.